Mary Brickell Village & SW 1 Avenue Roadway & Drainage Improvements
Current Work Status:
SW 10th Street:
- Working to complete milling & resurfacing on SW 10th Street. Work is estimated to be completed in February 2023.
SW 9th Street:
- Drainage work –Work on SW 9th Street has been mostly completed and is only pending the replacement of missing brick pavers on the NE quadrant of SW 9th Street & SW 1st Avenue.
SW 1st Avenue:
- Work is being performed one lane at a time, from North to South –Tentative milling & resurfacing on SW 1st Avenue during the 2nd week of February 2023.
Work Completed:
-
SW 7th Street to SW 8th Street – milling, resurfacing and temporary striping work is complete on this segment!
-
SW 9th Street to SW 11th Street – manholes adjusting and leveling work on these three streets (SW 9th, 10th and 11th Streets on SW 1st Avenue)
-
SW 11th Street - milling, resurfacing and temporary striping work is complete on this segment!
-
SW 12 Street - milling, resurfacing and temporary striping work is complete on this segment!
Construction in progress





Project No.: 40-B30637 & 40-B30833
Locations
SW/SE 9 Street from SW 1 Avenue to South Miami Avenue
SW/SE 10 Street from SW 1 Avenue to SE 1 Avenue (Brickell Plaza)
SW/SE 11 Street from SW 1 Avenue to South Miami Avenue
SW/SE 12 Street from SW 1 Avenue to South Miami Avenue
SW 1 Avenue from SE 7 Street to SW 15 Road
This project is Located in District 2
Notice of Construction Work
The City of Miami will be making much needed improvements and repairs during the next few months. Personnel and equipment from V. Engineering & Consulting Corp. will be working in your neighborhood during this time.
Scope of Work
Pavement Restoration
Drainage Improvements
New concrete sidewalks
New Curb and Gutter
Medians
New ADA ramps
Landscaping
Pavement markings
Signage
Construction Timeframe
Construction for this project is anticipated to commence in July 2019 and is anticipated to be completed by 2022. Please note that this schedule may be subject to change due to adverse weather or other unexpected conditions.
Estimated Construction Cost
$ 1,279,675
Contractor
V. Engineering & Consulting Corp.
Construction Hours
Monday through Friday, 8am to 5pm
Maintenance of Traffic (MOT)
Starting July 22, 2019 temporary traffic changes will be in place to ensure the work zone is safe during work. Motorist are asked to take extra care, keep to displayed speed limits and observe traffic controls and signage when traveling through work areas.
Construction is set to begin on SW 12 Street from SW 1 Avenue to South Miami Avenue.
If you have any questions or require additional information, please contact
Downtown/Brickell Neighborhood Enhancement Team (NET) at (305) 960-5135.
Office of Capital Improvements (OCI)… Building Better Neighborhoods and future for Miami.