Legion Park Community Building Improvements, District 5

 2-MRG-Logo-FINAL.jpg     Miami-Forever-Bond.png     OCI-Rectangle-Logo-BEST.jpg

The City of Miami, District 5 Commissioner Christine King, the Department of Parks and Recreation,
and the Office of Capital Improvements proudly announce the reconstruction of the Legion Park Community Center!  

Park Location: 6447 NE 7th Avenue, Miami, FL 33138

Community Building - OCI Construction Status - January - March 2024.

  • Electrical rough installation completed
  • Mechanical rough installation is at100%
  • Plumbing rough installation is completed
  • Dry wall installation is completed
  • Windows 2nd floor installation is completed
  • Shingle Roofing is completed.
  • Elevator installation is completed.
  • Installation of tiles in the bathrooms is completed, as well as terrazzo flooring in the exterior bathroom area.
  • Replacement of HVAC (new air conditioning) to be completed by the end of March 2024

 

New Restroom at Legion Park Community Center 1

New Restroom Sinks in Legion Park Community Center     New Water Fountains in Legion Park Community Center

New Kitchen Sinks at Legion Park Community Center

Newly Installed Shingle Roof on Legion Park Community Center 1     Newly Installed Shingle Roof on Legion Park Community Center 3

Legion Park Community Building Construction Main Large Room (Inside)

Legion Park Building Construction Photo (Inside)    Photo of Legion Park Roof Repair  

Legion Park Building Construction Photo (Inside)    Legion Park Community Building Construction (Inside)

The front of the Legion Park Community Building          

New and improved elements in the building will include:

  • Re-roofing of existing shingle roof (possibility of a clay barrel tile roof is being evaluated)
  • Upgrade/remodel of bathrooms
  • New warming kitchen
  • Terrace repairs and new landscaping
  • New elevator and fire alarm system
  • New acoustical ceilings, interior layout modifications and replacement of selected doors and windows
  • Second floor finishes and cabinetry
  • Miscellaneous repairs of exterior walls
  • Milling and resurfacing of existing parking lot and sidewalks repairs
  • New tennis court and resurfacing of existing tennis court

While the building is in construction, a rental trailer will be available on-site to maintain the park’s programming for school children.

 
First Floor Design Plan and Materials (click here(PDF, 11MB) to download the PDF version of the image below)

CM-Legion-Park_Board-1.jpg

 

Second Floor Design Plan (click here(PDF, 7MB) to download the PDF version of the image below)

CM-Legion-Park_Board-2.jpg

 

Restroom Materials Details

Legion-Park-Restroom-Materials.jpg

Exterior Community Terrace
Legion-Park-RENDERING-2.jpg

Side view of the Community Center
Legion-Park-RENDERING-1.jpg


Click here(PDF, 1MB) to download the Legion Park Community Building Exterior Elevations document
Legion-Park-Building-ELEVATIONS_1.jpg

Click here(PDF, 1MB) to download the Legion Park Community Building Site Plan document
Legion-Park-Community-Building-SITE-PLAN.jpg

 

Provide your feedback about this project here